How do you build a rehab budget for a Chicago two-flat?

Illustration of a brick Chicago two-flat with stacked bay windows and a renovation dumpster at the curb

Build a two-flat budget from contractor bids on each scope line, add the contractor's overhead and profit, and hold contingency in cash. The builder totals 17 lines and checks the result against up to 90% of purchase price plus 100% of approved rehab, capped at 75% of supported ARV. Its starting figures are examples, not cost data.

Scope
Markup
Leave at 0 if your bids already include it.
Reserve for what opens up behind the walls.
Loan check

Result

$266,560Budget to submit
$26,656Contingency to hold in cash
$111Cost per square foot
$116,560Down payment at this budget

The math

Scope lines
Demolition and dumpsters
3.8% of trade costs
$9,000
Masonry: tuckpointing, lintels, parapets
5.9% of trade costs
$14,000
Roof and gutters
5% of trade costs
$12,000
Rear porch and stairs
6.7% of trade costs
$16,000
Structural and framing
3.4% of trade costs
$8,000
Windows and exterior doors
5.9% of trade costs
$14,000
Plumbing, both units and service
9.2% of trade costs
$22,000
Electrical, service and both panels
8.4% of trade costs
$20,000
HVAC, two systems
7.6% of trade costs
$18,000
Insulation and drywall
7.1% of trade costs
$17,000
Kitchens x 2
10.9% of trade costs
$26,000
Bathrooms x 2
7.6% of trade costs
$18,000
Flooring and trim
6.3% of trade costs
$15,000
Paint and finish
3.8% of trade costs
$9,000
Basement and mechanical room
2.5% of trade costs
$6,000
Site, garage and fencing
2.1% of trade costs
$5,000
Permits, architect, expediter
3.8% of trade costs
$9,000
Trade costs$238,000
Contractor overhead and profit
12% of trade costs
$28,560
Budget to submit
The scope of work a lender reviews
$266,560
Contingency
10% of budget, not financed
$26,656
All-in rehab number$293,216
Loan check
Cost-based limit$482,560
ARV cap$390,000
Loan amount$390,000
Rehab holdback
Filled first, released by draw
$266,560
Funded toward the purchase
Loan minus holdback
$123,440
Down payment on the purchase
Larger than the cost-based figure because the ARV cap is binding
$116,560
Rehab you fund yourself
Covered by the holdback
$0

Starting figures are example inputs, not cost data. Replace every line with your contractor’s bid.

Largest lines: Kitchens x 2, Plumbing, both units and service, Electrical, service and both panels. Get a second bid on each.

The 75% ARV cap sets this loan, so it covers less than the cost-based limit.

Estimates for planning, not a loan offer or a closing figure. Program limits from Jaken Finance Group as of November 26, 2026.

The formula

  1. Trade costs = sum of scope lines.
  2. Budget to submit = trade costs + contractor overhead and profit.
  3. Contingency = budget x contingency percent, held in cash outside the loan.
  4. Loan check sizes a loan on your price, this budget and your ARV.

The result shown before you type anything is a worked example using the starting inputs. It is computed with the same code your inputs run through.

On this page
  1. Are the starting figures real Chicago costs?
  2. How do you fill the seventeen scope lines?
  3. How are overhead, contingency and cost per foot calculated?
  4. What does the loan check show, and what does it hide?
  5. Which Chicago rules change a scope line?
  6. What is the builder not designed to do?

A two-flat is two homes stacked in one building, with a shared roof, a shared rear porch and two of nearly everything inside. A single-family estimating form misses half of it. This builder lists the lines a two-unit Chicago building actually has, so the walkthrough has a checklist.

Jaken Finance Group, a lender, publishes this site. The builder's output is a planning estimate, not a bid, an appraisal or a loan approval.

Are the starting figures real Chicago costs?

No. The figures in the form when the page loads are example inputs that make the arithmetic visible. They are not survey data, not averages and not typical Chicago prices. Do not quote them to a seller, a partner or a lender. Overwrite every line with a number from a contractor who has seen the building. The article on how scope drives rehab cost explains how scope level, not a price list, drives the total.

How do you fill the seventeen scope lines?

Fill the lines in the order a contractor walks the building: outside in, then bottom to top.

  1. Shell. Demolition, masonry, roof, rear porch, structure, windows. Get masonry and porch numbers from trades who do that work; the masonry and porch rules page covers the permit side.
  2. Systems. Plumbing, electrical and HVAC, each priced for both units plus the service into the building.
  3. Interiors. Insulation and drywall, two kitchens, two baths, flooring, paint.
  4. Basement, site and soft costs. Mechanical room, garage, fencing, then permits, architect and expediter.
  5. Markup. Overhead and profit, contingency, finished square feet.
  6. Loan check. Purchase price and ARV.

Enter zero on lines that do not apply. Collect the bids with the three-bid comparison download, then carry the winner into the scope of work and budget form a lender reviews.

How are overhead, contingency and cost per foot calculated?

The builder adds the lines into trade costs, multiplies by the overhead and profit percentage, and calls the sum the budget to submit. Contingency is a percentage of that budget, shown separately because it is held in cash. Cost per square foot divides the budget by finished area.

Worked example

A $150,000 trade scope on a two-flat bought for $300,000

Four group subtotals stand in for the seventeen lines. Every amount is an illustrative input, not a price survey and not a typical Chicago cost.

Budget to submit

LineAmountHow it is figured
Shell: demolition, masonry, roof, porch, structure, windows$52,000
Systems: plumbing, electrical, HVAC$48,000
Interiors: drywall, kitchens, baths, floors, paint$41,000
Basement, site, permits and design$9,000
Contractor overhead and profit$18,00012% of $150,000 trade costs
Contingency, held in cash$16,80010% of the budget, outside the loan
Cost per finished square foot$762,200 square feet
Budget to submit$168,000

Line items sum to the stated result. Checked in code at build.

Loan check at $560,000 ARV

LineAmountHow it is figured
Funded at closing toward the price$252,000loan minus holdback
Rehab holdback$168,000the full budget
Cost-based limit$438,000what the loan would be without the ARV cap
Down payment on the purchase$48,000$18,000 more than the cost-based limit would require
Loan amount, set by the ARV cap$420,000

Line items sum to the stated result. Checked in code at build.

Assumptions

  • Loan limits are the published program; no rate is involved in this tool.
  • The holdback is filled first, so an ARV-capped loan shows up as a smaller closing advance, not a rehab shortfall.

What does the loan check show, and what does it hide?

The loan check sizes a loan on your price, this budget and your ARV, using the same limits as every tool here: the lower of the cost-based limit and the ARV cap. Read it with care. When the cap binds, the result still reports the full budget as covered and zero rehab to fund yourself, because the rehab holdback is filled first. The shortfall has moved to the purchase side, where less is funded at closing and your down payment is larger. The builder does not print that down payment; the worked example does.

Which Chicago rules change a scope line?

Four local rules move numbers in this form.

  • Who can run the job. The Department of Buildings requires a general contractor license for permitted work done as an investment or to sell or lease, unless you contract with a licensed general contractor who supervises the work.
  • What needs a permit. The City's no-permit list covers finish work and drywall replacement of Up to 1,000 square feet, and masonry replacement of Up to 50 square feet, in-kind. A gut rehab passes those limits on the first day.
  • Porches and masonry. Both are permitted worktypes in the Express Permit Program, not exempt repairs.
  • Lead-safe work. The EPA's RRP rule applies to paid work that disturbs paint in housing built before 1978, so check the year your building went up before pricing demolition, windows and paint.

What is the builder not designed to do?

The builder does not estimate anything. It will not tell you what a roof costs, sequence the work, or schedule draws; the tool that schedules draws takes the finished budget from here. It ignores carry, financing cost and resale.

For the financing side, JFG's two-flat and three-flat financing guide is the deeper read, and its national capital stack calculator treats improvements as a single number. This form is where that number gets built, line by line, for a two-unit Chicago building. Start with the two-flat property guide if you have not bought one before, or browse all calculators.

Questions: Two-flat rehab budget builder

Should contractor overhead and profit be a separate line or inside each bid?

Match how your contractor bids. If a general contractor gives you one lump sum per trade with markup already inside, set the overhead field to zero so it is not counted twice. If you received subcontractor numbers and the general contractor adds a fee on top, enter that percentage. The budget to submit should match the signed contract.

Why is contingency kept outside the budget the lender sees?

The builder treats contingency as your reserve, not as financed scope. A lender reviews a scope of work with defined line items and releases the holdback against completed work on those items. An undefined overrun reserve has nothing to inspect. Holding it in cash also keeps it available on the day a surprise appears, without waiting on a change order or a draw.

How accurate is the cost per square foot figure?

It is a ratio of your own inputs, nothing more. Use it to compare bids on the same building, or to spot a line that looks out of proportion, but do not compare it with a figure from another property unless both include the same scope. A two-flat with new masonry, porch and both kitchens will always sit above one that needed finishes only.

Can I use the builder for a three-flat or a single-family house?

You can, by reinterpreting the lines. The labels assume two kitchens, two baths, two heating systems and two electrical panels, so enter the total for however many you have and ignore the count in the label. For a house, leave the rear porch line at zero if there is no multi-story porch.

What should the permits, architect and expediter line include?

Include every cost of getting legal permission to build: drawings, the architect's or structural engineer's fee, the City's permit fees, and an expediter if you hire one. Plan-based permit applications in Chicago carry an upfront deposit of $600 non-refundable. Fees are tied to scope, so price this line after your architect confirms which review track the project needs.

Local rates and rules cited on this page

ItemFigurePrimary sourceEffective
No-permit limit for drywall or plaster replacementUp to 1,000 square feetWhat Types of Work Do Not Require a Building Permit? (Full List) (City of Chicago Department of Buildings)2026
Masonry replacement without a permitUp to 50 square feet, in-kindWhat Types of Work Do Not Require a Building Permit? (Full List) (City of Chicago Department of Buildings)2026
Plan-based permit application deposit$600 non-refundableDepartment of Buildings Changes for 2026 (City of Chicago Department of Buildings)2026-01-06

Rates as of November 25, 2026. Confirm with the agency before relying on any figure.

Sources

  1. General Contractor License, City of Chicago Department of Buildings, 2026.
  2. What Types of Work Do Not Require a Building Permit? (Full List), City of Chicago Department of Buildings, 2026.
  3. Express Permit Program, City of Chicago Department of Buildings, 2024-09-16.
  4. Lead Renovation, Repair and Painting Program, U.S. Environmental Protection Agency, 2026.
  5. Department of Buildings Changes for 2026, City of Chicago Department of Buildings, 2026-01-06.
Written and reviewed by Jason Taken, Principal, Jaken Finance Group. Author bio on jakenfinancegroup.com.Published November 25, 2026. Last updated November 25, 2026. Program terms as of November 26, 2026.General education only, not legal, tax or zoning advice. Confirm with local counsel or a CPA.