Each extra day on a flip costs one day of interest on the loan balance plus one day of taxes, insurance and utilities. The calculator divides annual interest by 360 and annual carry by 365, multiplies by the days lost, adds any extension fee you enter, and shows the share of profit consumed.
Result
The math
| Per day | |
|---|---|
| Interest $301,000 x 11% / 360 | $91.97 |
| Taxes, insurance, utilities $970 x 12 / 365 | $31.89 |
| Cost per day | $123.86 |
| Over 45 days | |
| Daily cost x days | $5,573.70 |
| Extension fee 0% of loan balance | $0.00 |
| Total cost of the delay | $5,573.70 |
| Against the deal | |
| Projected profit before delay | $55,000 |
| Profit after delay | $49,426.30 |
Rate entered: 11%. Published range: 8.99%-13.5% interest-only, 1-3 points. Your rate is set in underwriting.
Interest uses a 360-day year, a common convention in short-term lending. Check your note.
Extension and default terms are underwritten file by file; ask your loan officer before you assume a figure.
Estimates for planning, not a loan offer or a closing figure. The rate is your input. Program limits from Jaken Finance Group as of November 26, 2026.
The formula
- Interest per day = loan balance x annual rate / 360.
- Carry per day = monthly taxes, insurance and utilities x 12 / 365.
- Delay cost = (interest per day + carry per day) x days + any extension fee.
The result shown before you type anything is a worked example using the starting inputs. It is computed with the same code your inputs run through.
On this page
A schedule slip feels abstract until it has a price. Thirty days of waiting on a plan correction does not show up as an invoice. It shows up at payoff, as a smaller wire.
The calculator above converts days into dollars. Its output is an estimate built on the balance and rate you type, and its publisher is a lender, Jaken Finance Group. No figure on this page is an offer of credit.
What counts as a day of delay?
A day of delay is any day between purchase closing and resale closing that your original schedule did not include. The cause does not matter to the math: a permit under review, a failed rough inspection, a contractor who leaves for another job, or a finished house with no accepted offer all cost the same per day. Count calendar days, because interest does.
Which three numbers drive the result?
Three inputs do nearly all the work.
| Input | Where to find it | Default shown |
|---|---|---|
| Loan balance accruing interest | Latest lender statement, or the loan amount on your term sheet | Balance from the site's starting deal |
| Interest rate | Your note. The published range is 8.99%-13.5%, interest-only | An example rate, yours to replace |
| Taxes, insurance, utilities per month | Tax bill divided by twelve, insurance declarations page, last utility bills | Sum of the starting deal's three lines |
The rate box is an input, displayed next to the published range, and typing a number there does not make it your rate. Projected profit is optional; enter it to see the share a delay consumes.
How is the daily figure built?
The daily figure is interest per day plus carry cost per day. Interest per day is the balance times the annual rate divided by 360. Carry per day is monthly taxes, insurance and utilities times twelve, divided by 365. Multiply the sum by the days lost, then add an extension fee if one applies.
Sixty lost days on a $412,000 balance
A three-flat rehab that slips two months between a permit correction and a relisting. Illustrative inputs through the calculator's own function.
Cost of the slip
| Line | Amount | How it is figured |
|---|---|---|
| Interest, 60 days | $7,038.60 | $412,000 x 10.25% / 360 = $117.31 a day |
| Taxes, insurance, utilities, 60 days | $2,268.60 | $1,150 x 12 / 365 = $37.81 a day |
| Extension fee | $0.00 | left at zero; not a published term |
| Projected profit before the delay | $68,000 | |
| Profit after the delay | $58,692.80 | |
| Total cost of 60 days | $9,307.20 |
Line items sum to the stated result. Checked in code at build.
At $155.12 a day, the slip takes 13.69% of the projected profit before any price cut or extension fee.
Assumptions
- 10.25% is a rate typed in for the example. It falls within the published 8.99%-13.5% and is not a quote.
- The whole loan is assumed outstanding for every day of the delay.
Where do Chicago flips lose days?
Chicago flips lose days at permitting, at inspections and at the closing table. Three sourced reference points help you pick a realistic number of days:
- The Department of Buildings asks for At least 4 business days of notice when you request a permit inspection for a specific date, so plan on several business days before any re-inspection.
- A self-certified permit is typically issued 10 business days after zoning approval, and only when contractor licenses are valid and the property has no open violations or stop work orders.
- Starting without a permit is the expensive delay. The City says work stops until the permit is obtained and a penalty is paid: $1,000 or more, and permit fee usually tripled, per its guide to building permits.
The page on DOB permit review tracks compares them, and winter work rules cover the seasonal stops.
Why is the extension fee box empty?
The extension fee box starts at zero because extension terms are not published. If a delay pushes you past the maturity date, the cost of more time is set in your loan documents and by your lender at that moment. Enter the figure from your own documents. The page on flips that run long explains how to raise the issue early.
What does a delay cost that the calculator cannot price?
The calculator prices time, not consequences. It leaves out a price reduction after a stale listing, a contractor's remobilization charge, a second round of permit fees, and the next deal you could not start. It also assumes a level balance. Resale timing has its own federal wrinkle: under 24 CFR 203.37a, the clock from your acquisition to a resale contract reads: Ineligible for FHA financing at 90 days or less. Finishing very early does not always mean selling early.
What do you do with the daily number?
Use the daily number to make decisions that trade money for time. If an expediter, a second crew or a self-certifying architect costs less than the days saved times the daily figure, the spend pays for itself. Put the same figure in your milestone-by-milestone timeline next to each milestone, and compare your plan with the typical offer-to-payoff schedule. For hold lengths in whole months, see the whole-month carry tables.
JFG's national fix and flip calculator handles time as one hold-period field in months. This tool isolates the slip itself, by the day, with Chicago's permit checkpoints beside it. Find the other calculators in the tools section.
Questions: Delay cost calculator
Why is interest divided by 360 and carry by 365?
Many short-term commercial notes compute daily interest on a 360-day year, which makes each day slightly more expensive than a 365-day count would. Property tax, insurance and utilities are annual or monthly bills with no such convention, so the calculator spreads them over the calendar year. Your promissory note states which day count applies. If it says 365, the interest line is 360/365 of the figure shown.
What balance should I enter if my loan charges interest only on drawn funds?
Enter the balance that will be outstanding during the delay, not the full commitment. A delay at the permit stage happens when little of the rehab holdback has been drawn, so the balance is close to the closing advance. A delay at resale happens after the final draw, when the whole loan is out. The same number of days costs more late in the project.
Is a delay before closing on the purchase counted here?
No. This calculator prices days after you own the property and the loan is accruing. A slow purchase closing costs something different: possibly a contract extension or lost earnest money, but no loan interest. Once you close, every day counts, including days when no work is happening because a permit or a contractor is not ready.
How do I price a delay that falls in winter?
Raise the monthly carry figure before you run it. A vacant building in a Chicago winter still needs heat to protect plumbing, so utilities climb, and some exterior work such as masonry and concrete may have to wait for weather, which lengthens the delay itself. Run the calculator twice, with summer and winter carry, to see the spread on your own building.
Does the daily cost change if I am paying cash instead of borrowing?
The interest line goes to zero, but the carry line stays, and your cash has a cost too. Enter zero for the loan balance to see taxes, insurance and utilities alone. To price the tied-up cash, enter the amount you have in the deal as the balance and the return you would otherwise earn on it as the rate.
Local rates and rules cited on this page
| Item | Figure | Primary source | Effective |
|---|---|---|---|
| Permit inspection request lead time | At least 4 business days | Permit Inspections (City of Chicago Department of Buildings) | 2026 |
| Self-Certification typical issuance time | 10 business days after zoning approval | Self-Certified Permit Application Program (City of Chicago Department of Buildings) | 2026 |
| Stop work order penalty (City guidance) | $1,000 or more, and permit fee usually tripled | What happens if I start work without a required building permit? (City of Chicago Department of Buildings) | 2026 |
| FHA anti-flipping: resale within 90 days | Ineligible for FHA financing at 90 days or less | 24 CFR 203.37a - Sale of property (eCFR / HUD) | 2006-06-07 |
Rates as of November 25, 2026. Confirm with the agency before relying on any figure.
Sources
- Permit Inspections, City of Chicago Department of Buildings, 2026.
- Self-Certified Permit Application Program, City of Chicago Department of Buildings, 2026.
- What happens if I start work without a required building permit?, City of Chicago Department of Buildings, 2026.
- 24 CFR 203.37a, Sale of property, eCFR / HUD, 2006-06-07.