Give three contractors the same written scope, enter each bid line by line, and compare them only after every bid covers the same work. The spreadsheet shows the lowest price, the low bidder and the high-to-low spread on each line. A second sheet records license, insurance, references, payment terms and warranty.
Contractor Bid Comparison and Qualification Sheet
Level three bids against one scope, see the low number and the spread on every line, and vet the contractor before you sign.
On this page
- What is bid leveling, and why not take the low number?
- How do you set up the three bid columns?
- What do the Lowest and Spread columns tell you?
- How do you vet a Chicago contractor before price matters?
- What is in the bid comparison and qualification sheet?
- Which payment terms fit a loan funded in draws?
- What does your lender need from the winning bid?
Three bids for the same two-flat can come back far apart, and the cheapest is often cheapest because something is missing from it. Bid leveling is the habit of finding out what, before you sign.
The sheet has two parts. One compares price on a common scope. The other compares the contractors themselves.
What is bid leveling, and why not take the low number?
Bid leveling means adjusting each bid until all of them price the same work, then comparing. You do it because raw totals are not comparable: one bid excludes the permit, another assumes you supply cabinets, a third skipped the porch.
The low number is only low if it is complete. On a financed flip an incomplete bid costs you twice, once when the missing work is added as a change order and again when the rehab holdback turns out to be sized from a budget that was too small.
How do you set up the three bid columns?
Start from one written scope. The scope of work template gives you the line items; the leveling sheet groups them into twenty-four comparison lines, from demolition to overhead and profit.
- Send every bidder the same scope, drawings and finish schedule on the same day.
- Walk the building with each one, roof and basement included.
- Ask for prices by line, with exclusions and allowances listed.
- Enter each bid in its column. Leave a cell blank where a bidder gave no price.
- Type the contractor names over the column headers. The low-bidder formula reads them.
Add a fourth figure if you have one: your own budget, built from the two-flat budget builder or from rehab cost ranges by scope.
What do the Lowest and Spread columns tell you?
Lowest is the minimum of the three bids on a line. Spread is the highest minus the lowest. A small spread means the bidders understood the line the same way. A large spread means they priced different work, and that is a question to ask, not a saving to bank.
| What you see | What it usually means | What to do |
|---|---|---|
| One bid far below the others on a line | Missing scope, or an unlicensed sub | Ask what is included, in writing |
| One bid far above | Bidder saw a problem the others missed | Ask what they saw |
| Blank cell | Excluded | Add a plug from another bid |
| All three close | Scope is clear | Compare on schedule and terms |
The total of the Lowest column is the sum of the best price on every line. Nobody offered that price. Use it to negotiate individual lines, never as your budget.
How do you vet a Chicago contractor before price matters?
Check the license first. The Department of Buildings says a general contractor license is required for most building construction, alteration and repair work in the city, and that electrical, plumbing and mason contractors hold their own City licenses. Ask who will pull each permit; the guide to DOB permit types explains what each one involves.
Then insurance, from the agent and not a photocopy: general liability and workers' compensation, with your entity as certificate holder. In a building from before 1978, ask for the firm's EPA lead-safe certification. EPA's RRP program requires firms paid to disturb painted surfaces in that housing to be certified.
Call references from jobs of similar size. Ask whether subcontractors were paid.
What is in the bid comparison and qualification sheet?
Project and bidders
Rules for a fair comparison
- Every bidder gets the same written scope, the same drawings and the same finish schedule
- Every bidder walks the building, including the roof and the basement
- Bids come back broken out by the scope lines below, not as one number
- Each bid states what is excluded and which items are allowances
- Each bid states who pays for permits, drawings, dumpsters and utility coordination
- Questions from one bidder are answered in writing to all three
- A line left blank by a bidder is treated as excluded until they confirm it in writing
Bid leveling sheet
Enter each bid by line. In the spreadsheet, Lowest and Spread calculate. A wide spread on one line means the bidders priced different work: go back and ask.
| Scope line | Your budget | Contractor A | Contractor B | Contractor C | Lowest | Spread (high minus low) | Included / excluded notes |
|---|---|---|---|---|---|---|---|
| Demolition and debris | |||||||
| Masonry and tuckpointing | |||||||
| Lintels, parapets and coping | |||||||
| Roof, gutters and downspouts | |||||||
| Porches, decks and stairs | |||||||
| Structural and foundation | |||||||
| Windows and exterior doors | |||||||
| Plumbing, including water service | |||||||
| Sewer | |||||||
| Electrical, including service | |||||||
| HVAC | |||||||
| Insulation | |||||||
| Framing and drywall | |||||||
| Kitchens | |||||||
| Bathrooms | |||||||
| Flooring | |||||||
| Interior doors and trim | |||||||
| Paint | |||||||
| Basement | |||||||
| Site work and garage | |||||||
| Permits, drawings and expediting | |||||||
| Dumpsters, cleanup and final clean | |||||||
| General conditions, supervision and insurance | |||||||
| Overhead and profit | |||||||
| Total bid | |||||||
Exclusions, allowances and plugs
To compare totals, add a plug for anything one bidder left out, using another bidder’s price for that line.
| Item | Excluded or allowance in which bid | Plug amount used | Source of the plug | Confirmed in writing (date) |
|---|---|---|---|---|
Contractor qualification
| Criterion | Contractor A | Contractor B | Contractor C | How to verify |
|---|---|---|---|---|
| City of Chicago general contractor license number and class | Department of Buildings list of licensed general contractors | |||
| Trade licenses for electrical, plumbing and masonry work | Department of Buildings trade license lists; ask which licensed subcontractors will pull each permit | |||
| General liability insurance: carrier, limits, expiration | Certificate of insurance sent to you by the contractor's agent, naming your entity as certificate holder | |||
| Workers' compensation insurance | Same certificate; confirm it covers the crew that will be on site | |||
| EPA lead-safe certified firm (pre-1978 buildings) | EPA certified renovation firm search | |||
| Three references from jobs of the same size in the last two years | Call them. Ask about schedule, change orders and whether subs were paid | |||
| Permit history: recent permits issued under this license | Department of Buildings permit records; ask for three permit numbers | |||
| Who supervises the job daily, and how many jobs they run at once | Interview | |||
| Proposed start date and duration | Written in the bid | |||
| Payment terms: deposit, progress payments, retainage | Written in the bid. Payments should follow completed work so they line up with lender draws | |||
| Change order process and markup | Written in the contract | |||
| Lien waivers and sworn statement with every payment | Written in the contract; required of the owner under Section 5 of the Illinois Mechanics Lien Act | |||
| Warranty: length and what is covered | Written in the contract | |||
| Capacity to float work between draws | Ask directly. A contractor who needs cash up front will stall when a draw is late |
Award decision
Reading the results
- The sum of the lowest line from each bidder is not a price anyone offered. Use it to see where each contractor is high, not as your budget.
- The lowest total is only the lowest after the bids cover the same scope. Level first, then compare.
- A bid far below the other two on plumbing, electrical or masonry usually means missing scope or an unlicensed sub.
- In Chicago a general contractor license is required to do most construction, alteration and repair work for compensation or as an investment. Confirm the license before you compare price.
- Send the lender the scope and budget that match the contract you sign. The rehab holdback is sized from it.
Which payment terms fit a loan funded in draws?
Terms that pay for finished work fit; terms that pay ahead of it do not. Your lender releases each draw after work is in place and inspected, so a contract that wants half up front leaves you funding the difference.
Write two things into the contract. First, payment by phase, matching the draw phases in your scope. Second, a lien waiver and an updated sworn statement with every payment. Under Section 5 of the Illinois Mechanics Lien Act, the owner has a duty to require the contractor's sworn statement of who is furnishing labor and material, and what each is owed, before paying. This is general information, so have your attorney review the contract.
Ask each bidder directly whether they can carry a phase between draws. It is the last row of the qualification sheet for a reason.
What does your lender need from the winning bid?
Your lender needs the budget it approves to match the contract you sign. Update the scope amounts to the winning bid, attach the contract, the license number and the insurance certificate, and send them together. Jaken Finance Group's guide to starting flips in Chicago covers building the team around that contractor.
If this is your first project, the first flip checklist puts contractor selection in sequence with everything else. The remaining worksheets are in the full list of downloads.
Questions: Contractor bid comparison sheet
Is three bids enough for a flip rehab?
Three is the working minimum because it lets you see an outlier. With two bids you only know they differ; with three you can tell which contractor is out of line on plumbing or masonry. More than four rarely adds information and costs you weeks of walkthroughs. If you cannot get three complete bids, get two full ones and a trade-only price from a plumber or mason for the largest line as a cross-check.
What do I do when a contractor refuses to break the bid into lines?
Ask once more and explain why: your lender funds the rehab in draws tied to scope lines, so a single number cannot be paid out. Offer the scope sheet with blank price columns for the contractor to fill in. A contractor who still will not itemize is telling you how change orders and draw requests will go. Record the lump sum in the totals row, note the refusal, and weigh it.
How should I treat allowances in a bid?
An allowance is a placeholder, not a price. Record each one in the exclusions and allowances table with the amount and what it is meant to cover: cabinets, tile, light fixtures. Then compare the allowance with what your finish level will really cost. Two bids can look identical while one carries a cabinet allowance half the size of the other, which only shows up when the order is placed.
Can I act as my own general contractor in Chicago to save the markup?
Read the Department of Buildings' license page before you plan on it. It says a general contractor license is required to undertake regulated work for compensation, as an investment, or with the intent to sell or lease the property, and the owner exception it describes is for an individual's own primary residence. A flip is an investment by definition. Budget for a licensed general contractor, and confirm the rule with the Department or your attorney.
Should the lowest leveled bid always win?
No. Price is one row of the decision. A contractor who is slightly higher but licensed, insured, available next week and able to carry a phase of work between draws will usually finish cheaper once interest and delay are counted. Use the qualification sheet to score the things price hides, and write your reason on the award line so you can explain the choice to a partner or lender later.
Sources
- General Contractor License, City of Chicago Department of Buildings, 2026.
- Mechanics Lien Act, Section 5 (770 ILCS 60/5), Illinois General Assembly, P.A. 103-827, eff. 2025-01-01.
- Lead Renovation, Repair and Painting Program, U.S. Environmental Protection Agency, 2026.