Chicago Fix & Flip LoansPublished by Jaken Finance Group

How do you write a scope of work a rehab lender will fund?

Illustration of a gutted interior mid-rehab with open stud walls, exposed joists and a common-brick party wall

Write one line per trade item, each with a description an inspector can verify, a quantity, labor and material dollars, and the draw in which it will be finished. The template lists the lines a Chicago rehab usually needs and totals them. Amounts are blank on purpose: the prices come from your bids.

Free download, no email required

Chicago Rehab Scope of Work and Budget Template

Trade-by-trade scope lines for a Chicago rehab, with labor, material, line totals and draw phases. Amounts are blank: the numbers come from your bids.

Version 1.0, November 25, 2026. The full document is also on this page below, so you can read it before you download it.
On this page
  1. Why does a lender want lines and not a total?
  2. How do you fill in one line, column by column?
  3. Which Chicago trades need their own line?
  4. What does the spreadsheet calculate?
  5. What is in the scope of work and budget template?
  6. Where do scopes go wrong on older Chicago buildings?
  7. How is the draw phase column used after closing?
  8. What should you do with the finished sheet?

A scope of work does two jobs on a financed flip. Before closing it sets the size of the rehab part of the loan. After closing it is the list every draw is paid against. A scope that reads "kitchen, baths, mechanicals" with one number at the bottom fails at both.

This template is built for the buildings Chicago flippers actually buy: brick two-flats, bungalows, frame cottages and greystones with old masonry, old wiring and a porch on the back.

Why does a lender want lines and not a total?

A lender wants lines because it releases the rehab money in pieces, and each piece has to match work an inspector can see. Jaken Finance Group describes its draws as staged against a rehab holdback, with inspections. A single lump sum gives the inspector nothing to measure, so the draw gets cut or delayed.

Lines also protect you. When the budget is itemized, you can see how much of the job is masonry before you buy, and you can check each figure against typical rehab costs by scope for Chicago housing stock.

How do you fill in one line, column by column?

Take the windows line as the pattern:

  1. Scope description. "Replace 14 double-hung windows, front and rear, including two basement egress windows." Say what, where and how many.
  2. Qty and unit. 14, each. Use square feet for roofing and drywall, linear feet for parapets and tuckpointing, lump sum only when nothing else fits.
  3. Labor and material. The extended dollars for the whole line, from the bid.
  4. Line total and % of budget. Calculated in the spreadsheet.
  5. Draw phase. The number of the draw in which all 14 are installed and trimmed.

Repeat that for each trade. Delete what does not apply.

Which Chicago trades need their own line?

Masonry, lintels, parapets, porches, the water service and the electrical service each get a line, because each is a common budget surprise on a Chicago building and several need their own permit or licensed trade. The Department of Buildings lists mason, electrical and plumbing contractors as separately licensed from the general contractor license.

A lintel that has rusted and lifted the brick above it is a masonry repair, not a window repair, and it will not show up in a window bid. The same goes for a parapet that looks fine from the sidewalk. The rules behind those lines are in the guide to masonry, porch and parapet work.

Soft costs are lines too: permit fees, drawings, an expediter. Which permit process applies changes both the fee and the weeks before work starts.

What does the spreadsheet calculate?

The Excel version adds labor and material into a line total, shows each line as a share of the direct cost subtotal, and carries the subtotal to a Budget Summary sheet. There you enter two percentages, contractor overhead and profit and your contingency, and it returns the grand total.

One more input matters: the rehab budget your lender approved. The sheet subtracts it from the grand total and shows the difference you fund from cash. Full rehab financing never means no cash. Closing costs, interest, overruns and work finished before a draw funds still come from you.

To test a budget before you have bids, the two-flat budget builder works through the same categories.

What is in the scope of work and budget template?

Project header

Property address and PIN
Property type and unit count (before and after)
Borrowing entity
General contractor and City of Chicago license number
Permit path and application number
Scope prepared by, and date
Bid or contract this budget is based on

How to fill in each line

  • Scope description: say what is being done, where and to what standard. "Replace 14 double-hung windows, front and rear elevations" can be inspected. "Windows" cannot.
  • Qty and unit: count, square feet, linear feet or lump sum. A lender inspector uses these to judge percent complete.
  • Labor and material: enter the extended dollars for the whole line, not a unit price. Line total is labor plus material.
  • Draw phase: the number of the draw in which the line will be finished. A line split across two draws should be two lines.
  • Delete lines that do not apply. Do not leave a line with a scope and no dollars, or dollars and no scope.
  • Keep contingency out of the trade lines. It is its own line in the budget summary.

Exterior, masonry and structure

Line itemScope descriptionQtyUnitLaborMaterialLine totalDraw phase
Demolition and debrisSelective or full gut, dumpsters, haul-off, street or alley dumpster permit
Masonry and tuckpointingElevations to grind and repoint, brick replacement, chimney, sealing
LintelsCount of openings, steel replacement, flashing, brick relaid above
Parapets and copingRebuild height and length, coping stones or metal cap, flashing
RoofTear-off or overlay, membrane or shingle type, decking, gutters and downspouts
Porches, decks and stairsRepair or rebuild, stamped drawings and permit, guards and stairs
StructuralBeams, columns, joist sistering, foundation, engineer letter
Windows and exterior doorsCount by size, egress windows, glass block removal, trim and capping
        
        

Mechanical systems

Line itemScope descriptionQtyUnitLaborMaterialLine totalDraw phase
Plumbing: supply, drain and ventStacks, branch lines, fixtures roughed, water heaters
Plumbing: water serviceService line material and size, meter, replacement from the main if required
SewerCamera inspection, repairs, cleanouts, catch basin
Electrical: serviceService size, meters per unit, panel locations, utility coordination
Electrical: distributionRewire extent, conduit, devices, fixtures, smoke and CO detectors
HVACFurnaces or boilers, condensers, ductwork, venting, one system per unit
Gas pipingMeters, piping to appliances, pressure test
        
        

Interior build-out and finishes

Line itemScope descriptionQtyUnitLaborMaterialLine totalDraw phase
Framing and layout changesWalls moved, stairs, subfloor repair, fire separation between units
Insulation and air sealingWalls, attic, rim joists, sound batts between units
Drywall and plasterHang, tape and finish; plaster patching; ceilings
KitchensCabinets, counters, sink, appliances, backsplash, per kitchen
BathroomsTub or shower, tile, vanity, toilet, exhaust fan, per bath
FlooringRefinish hardwood, new plank, tile, carpet, stairs
Interior doors, trim and hardwareDoor count, casing and base, closet systems
PaintInterior walls, ceilings and trim; exterior trim; lead-safe prep where required
BasementWaterproofing, drain tile, sump, slab, ceiling height, finish level
        
        

Site, garage and soft costs

Line itemScope descriptionQtyUnitLaborMaterialLine totalDraw phase
Site workConcrete walks, grading, fencing, landscaping, tree work
GarageRepair or rebuild, overhead door, roof, electrical, alley apron
Building permit feesDepartment of Buildings permit fees for the chosen permit path
Architect or engineerDrawings, structural letter, stamped porch plans
Permit expediterFiling, corrections and pickup
EnvironmentalLead-safe work practices, asbestos survey or abatement, mold
Final cleaning and punch listConstruction clean, touch-up, final walkthrough items
        
        

Budget summary

In the spreadsheet these lines calculate. On paper, carry the totals down by hand.

LinePercentAmountNotes
Direct cost subtotal (sum of all line totals)
General contractor overhead and profitPercent of the direct cost subtotal
ContingencyPercent of the direct cost subtotal
Grand total rehab budget
Rehab budget approved by the lenderFrom the term sheet or loan approval
Difference you fund from cashGrand total minus the approved budget

Chicago items that get missed

Walk the building with this list before you call the scope finished.

  • Parapets, coping and chimneys checked from the roof, not from the sidewalk
  • Every steel lintel checked for rust jacking and stair-step cracks in the brick above
  • Porches and decks: repair or replacement generally needs a Department of Buildings permit with drawings
  • Water service line material identified, and replacement priced if it is in your scope
    Many older Chicago buildings are still served by a lead service line. Ask the Department of Water Management or your plumber what the records show.
  • Electrical service sized for the finished unit count, with one meter per unit
  • Lead-safe work practices priced for any painted surface disturbed in a building built before 1978
    The EPA Renovation, Repair and Painting Rule applies to firms paid to do this work, including for house flippers.
  • Open building violations: each one has a scope line that cures it
  • Winter conditions: temporary heat, masonry protection and exterior work sequencing
  • Dumpster and street-use permits, alley access and neighbor protection on a zero-lot-line building

Where do scopes go wrong on older Chicago buildings?

They go wrong where nobody looked. Three places account for most of it:

  • The roof line. Parapets, coping and chimneys are priced from the ground and rebuilt from the roof for more.
  • Behind the walls. Opening one wall for a kitchen exposes wiring or plumbing that then has to be corrected under the permit.
  • Paint. In housing built before 1978, EPA says its Renovation, Repair and Painting Rule applies to firms paid to disturb painted surfaces, and to people who buy, renovate and sell homes for profit. Lead-safe setup and cleanup are a cost; see the page on lead paint and the RRP rule.

How is the draw phase column used after closing?

After closing, the draw phase column becomes your draw schedule. Sort by phase and each group is one request: the lines you will claim, their total, and the photos you need. The process is explained in the guide to how rehab draws get released, and Jaken's draw process guide shows the lender's side.

Front-load carefully. Demolition and rough trades finish early but finishes carry much of the cost, so the last draw is often the largest and the slowest to release.

What should you do with the finished sheet?

Send the same version to three contractors and level their prices on the bid comparison sheet. Then update the amounts to match the contract you sign and send that version, not the estimate, to your lender. Other worksheets are in the templates and checklists hub.

Questions: Scope of work and budget template

Should the scope show unit prices or totals for each line?

Totals. Enter the extended labor dollars and the extended material dollars for the whole line, and let the sheet add them. Put the count or the measurement in the quantity and unit columns so an inspector can judge how much of the line is done. If your contractor bids by unit price, multiply it out before you enter it. A lender reads the line total and the description, not the arithmetic behind them.

Does a general contractor's overhead and profit go in the trade lines or on its own line?

Either works, but pick one and say which. If the bid shows markup separately, leave the trade lines at cost and enter the percentage on the Budget Summary sheet, where it is applied to the direct cost subtotal. If the bid already carries markup inside every line, leave the percentage blank. Entering it both ways double counts it, and a lender comparing your budget to the signed contract will catch the difference.

Can I change the scope after the loan closes?

You can ask, but treat the approved scope as the budget the loan was sized from. Moving money between lines or adding work normally needs the lender's written approval before the work is claimed on a draw. Added cost does not raise the holdback on its own, so most changes are paid from contingency or your cash. Keep a dated copy of each version of the sheet so the draw inspector and you are reading the same one.

How many lines is too many for a lender scope?

The template has thirty-one trade lines, and most rehabs will not use all of them. That is enough detail for an inspector to tie each draw to finished work without turning the sheet into a materials list. Split a line when it will be paid in two different draws or covers two trades with separate permits. Merge lines when neither the price nor the timing can be separated.

Do I need a separate scope for each unit in a two-flat?

One sheet is normal, with the unit named in the description where it matters: first-floor kitchen, second-floor bath, common stair. Shared systems such as the roof, masonry, water service and electrical service stay as single lines. Use separate lines per unit for kitchens, baths, flooring and heating equipment, because those finish at different times and an inspector will walk each unit on its own.

Sources

  1. Lead Renovation, Repair and Painting Program, U.S. Environmental Protection Agency, 2026.
  2. Permits, City of Chicago Department of Buildings, 2026.
  3. General Contractor License, City of Chicago Department of Buildings, 2026.
Written and reviewed by Jason Taken, Principal, Jaken Finance Group. Author bio on jakenfinancegroup.com.Published November 25, 2026. Last updated November 25, 2026. Program terms as of November 26, 2026.General education only, not legal, tax or zoning advice. Confirm with local counsel or a CPA.