How do you track rehab draws so the holdback never surprises you?

Illustration of a gutted interior mid-rehab with open stud walls, exposed joists and a common-brick party wall

Log every draw on one row: date requested, lines claimed, amount requested, inspection date, amount approved and date funded. The spreadsheet then calculates days to fund, cumulative funded and the holdback remaining from the holdback figure you enter once. A second sheet tracks lien waivers by payee.

Free download, no email required

Rehab Draw Request Log

One row per draw: what you claimed, what was approved, how long it took to fund and how much of the holdback is left.

Version 1.0, November 25, 2026. The full document is also on this page below, so you can read it before you download it.
On this page
  1. What does one row of the log record?
  2. Why log the days to fund?
  3. How do the holdback formulas work?
  4. Which paperwork belongs with each request?
  5. What is in the draw request log?
  6. What does a lender check before releasing a draw?
  7. When does the log tell you to bring cash?
  8. Where does the log fit with the other worksheets?

The rehab part of a flip loan is not handed over at closing. It sits in a rehab holdback and is released as work is finished and inspected. Between finishing a phase and receiving the wire, somebody is carrying the cost, and it is usually you or your contractor.

A draw log makes that gap a number you can plan around. It is a few minutes of data entry per draw, and it answers the question every flipper asks in month three: how much is left, and is it enough to finish?

What does one row of the log record?

One row records one draw from request to wire: draw number, date requested, the phase and scope lines claimed, amount requested, inspection date, amount approved, date funded, whether lien waivers and photos went in, and any retainage note. Three more cells calculate: days to fund, cumulative funded and holdback remaining.

Enter the lines claimed using the same names as your approved scope. If you built the budget on the scope and budget sheet, its draw phase column already groups the lines for you.

Why log the days to fund?

Days to fund tells you how much cash you need to float each phase. If your first two draws took nine and eleven days from complete request to wire, plan the next phase assuming ten, and make sure you or your contractor can pay for that stretch of work.

The totals row averages the figure across all funded draws. Slow draws also extend the hold, and every extra day has a price; the page on what a longer hold costs shows how that adds up.

How do the holdback formulas work?

You enter the holdback once, on the Holdback Summary sheet, from your closing statement. Each row of the log then shows cumulative funded, which adds approved amounts only for draws that have a funded date, and holdback remaining, which is the holdback minus that running total.

The summary sheet adds one input the lender never sees: your own cost to finish the remaining scope. Holdback remaining minus cost to finish is your cushion. When it turns negative, the job costs more than the loan has left, and the difference is cash you bring.

Summary lineWhere it comes from
Rehab holdback at closingYou enter it once
Total requested, approved and fundedTotals row of the Draw Log
Holdback remainingHoldback minus total funded
Cost to finishYou update it after each draw
Shortfall or cushionHoldback remaining minus cost to finish

Which paperwork belongs with each request?

Each request needs the lender's form, dated photos of every claimed line, lien waivers for the money paid out of the previous draw, and a current sworn statement from the contractor. The last item is Illinois law, not lender preference. Section 5 of the Mechanics Lien Act makes it the contractor's duty to give, and the owner's duty to require, a sworn written statement of everyone furnishing labor or material and the amounts due to each, before the owner pays the contractor.

A lien waiver from each payee is how you prove the last draw reached the people who did the work. Unpaid subcontractors can record a mechanics lien against a property you are trying to sell. The Lien Waivers sheet tracks them by draw and payee. This is general information; ask your attorney how the Act applies to your contract.

Where the claimed work needed a permit, include the inspection sign-off. The Department of Buildings lists its permit processes and each has its own inspection steps.

What is in the draw request log?

Loan and project

Property address
Borrowing entity
Lender and loan number
Draw contact at the lender: name, email, phone
Rehab holdback at closing
Number of draws planned
Inspection method (site visit, video or photos) and who orders it
Loan maturity date

Before you request a draw

A draw pays for work in place. Requests that fail usually fail one of these checks.

  • Every line you are claiming is finished, not started
    Partly finished lines are paid at the percent the inspector agrees to, or not at all.
  • The lines match the approved scope of work by name and amount
  • Permits for the claimed work are issued and posted, and rough inspections are signed off where required
  • Photos are dated, wide enough to show the room, and labeled with the scope line
  • Lien waivers from the general contractor and each subcontractor and supplier paid from the last draw are collected
  • The contractor's sworn statement is current
    Section 5 of the Illinois Mechanics Lien Act makes it the owner’s duty to require this statement before paying the contractor.
  • Change orders are approved in writing by the lender before the work is claimed
  • Loan payments, property taxes and insurance are current

Draw log

The spreadsheet calculates days to fund, cumulative funded and holdback remaining. On paper, carry the running total by hand.

Draw #Date requestedPhase and lines claimedAmount requestedInspection dateAmount approvedDate fundedDays to fundLien waivers receivedPhotos sentCumulative fundedHoldback remaining
            
            
            
            
            
            
            
            

Lien waiver tracker

One row per payee per draw. A final waiver is collected with the last payment to each payee.

Draw #Payee (contractor, sub or supplier)Amount paidWaiver type (partial or final)Date receivedSent to lender or title
      
      
      
      
      
      
      
      
      
      

What goes in each draw package

  • The lender's draw request form, signed
  • Scope of work marked with percent complete for each line claimed
  • Dated photos for each claimed line
  • Invoices or receipts if the lender asks for them
  • Lien waivers for the prior draw, and the sworn contractor statement
  • Permit card or inspection sign-offs for the work claimed
  • Approved change orders
  • Wire instructions on file, confirmed by phone if anything changed

Holdback reconciliation

Do this after every funded draw. If the remaining work costs more than the remaining holdback, you have a gap to fund from cash.

Rehab holdback at closing
Total approved to date
Holdback remaining
Your cost to finish the remaining scope
Shortfall or cushion (holdback remaining minus cost to finish)
Retainage held by the lender or by you, and the release condition

Notes on retainage and timing

  • Draws reimburse work already done, so you or your contractor carry the cost between finishing a phase and the wire. Record the real days to fund and plan the next phase around it.
  • Draw fees, inspection fees and any retainage are set by each lender and each loan. Write the terms from your loan documents in the retainage notes column; this log does not assume them.
  • If a draw is cut, ask which lines were reduced and why, fix them, and claim the balance on the next draw.
  • Keep the final draw for last: lenders commonly want final inspections, a clean punch list and final lien waivers before releasing it.

What does a lender check before releasing a draw?

A lender checks that the claimed lines are complete, that they match the approved scope, that the paperwork is in and that the loan is in good standing. A draw inspection confirms work in place; it is not a code inspection and does not replace one.

The full sequence is in the guide to requesting and receiving draws. Jaken Finance Group, which publishes this site, explains its own steps in its draw process guide. To map phases to dollars before the job starts, use the planner for draw phases.

When does the log tell you to bring cash?

It tells you when the cushion line goes negative, and it tells you early. Update cost to finish after every draw. A shortfall found at draw two can be solved by trimming finish selections or adding cash on your schedule. The same shortfall found at the final draw stops the job a few weeks before listing, with interest running.

If the schedule is also slipping toward the maturity date, read what happens when a loan runs past maturity and call your lender before it does.

Where does the log fit with the other worksheets?

Start the log the day you close and enter the holdback from the settlement statement. The other worksheets in the ungated worksheet library cover the scope, the schedule and the cash you need on day one.

Questions: Draw request log

Is this log the form I send to my lender to request a draw?

No. Your lender has its own request form or portal, and that is what triggers an inspection and a wire. This log is your record of what you sent and what came back. Keep both. When a draw is approved for less than you asked, or a wire is slow, the log is where you see the pattern, and it is what you bring to a conversation with the lender's draw desk.

What counts as the date requested if I send documents in pieces?

Use the date the request was complete: form, photos, waivers and any permit sign-offs all delivered. A lender's clock starts when it has everything, so logging the first email makes the days-to-fund figure look worse than it is and hides the real cause, which is an incomplete package. If you want to track both, put the first-email date in the retainage notes column.

How should I record a draw that was only partly approved?

Enter the full amount you asked for under amount requested and the lower figure under amount approved. Write which scope lines were reduced, and why, in the lines-claimed cell. Then claim the balance on the next draw once the work is finished or the missing paperwork is in. The totals row keeps a running sum of both columns, so the gap between requested and approved is visible at a glance.

Does the log handle retainage held back from each draw?

It records it but does not assume it. Whether any retainage is held, how much and when it is released are set by your loan documents, so the sheet gives you a notes column and a reconciliation line instead of a built-in percentage. Draw fees are underwritten file by file, ask your loan officer. Write the terms from your own closing package in the first row so you are not reconstructing them at the final draw.

Should my contractor keep the same log?

Share it. A contractor who can see when each draw was requested, approved and funded can plan crews and material orders around real dates instead of promises. It also settles arguments about who was waiting on whom. Give the contractor view access to the spreadsheet and keep editing rights yourself, since the amounts approved come from the lender to you, not to the contractor.

Sources

  1. Mechanics Lien Act, Section 5 (770 ILCS 60/5), Illinois General Assembly, P.A. 103-827, eff. 2025-01-01.
  2. Permits, City of Chicago Department of Buildings, 2026.
Written and reviewed by Jason Taken, Principal, Jaken Finance Group. Author bio on jakenfinancegroup.com.Published November 25, 2026. Last updated November 25, 2026. Program terms as of November 26, 2026.General education only, not legal, tax or zoning advice. Confirm with local counsel or a CPA.