How long does a Chicago fix and flip take from offer to payoff?

Illustration of a brick Chicago two-flat with stacked bay windows and a renovation dumpster at the curb

A permitted Chicago flip runs about 189 calendar days from accepted offer to payoff in our sample: 21 days to close the purchase, then a 168-day hold. The citywide median wait for a self-certified renovation permit is 27 days, and 94 under Standard Plan Review. Jaken Finance Group closes in 7-10 business days.

Key facts
Attorney review
5 business days after the date of acceptance
Loan closing
7-10 business days on complete files, counted after borrower conditions are met
Median permit wait, self-certified
27 days citywide
Median permit wait, Standard Plan Review
94 days citywide
Resale buyer's loan contingency
45 days after acceptance or 5 business days before closing, whichever is earlier
Loan term
underwritten file by file, ask your loan officer

Program terms as of November 26, 2026. Rates as of November 25, 2026.

On this page
  1. What happens in the first five business days after acceptance?
  2. How fast can the loan and the purchase close?
  3. How long does a Chicago permit take once you apply?
  4. How many days should the rehab itself get?
  5. What does the full calendar cost in carry?
  6. When should the listing go live, and how long is the buyer's side?
  7. What happens at the resale closing and payoff?
  8. Where do Chicago flips lose the most days?
  9. What belongs on your calendar before the contract goes out?

National articles put a flip at four to six months and stop there. A Chicago flip has clocks those articles never mention: an attorney review period written into the contract, City certificates that gate the deed, and a permit queue whose length depends on the review program your architect files under.

This page lays those clocks end to end, as one stage of the Chicago flip process. Contract deadlines come from the Multi-Board Residential Real Estate Contract 8.0. Permit numbers come from the City's own permit records.

What happens in the first five business days after acceptance?

Two deadlines start the moment the seller accepts, and they run at the same time. The attorney review period is 5 business days after the date of acceptance, and the buyer's inspection notice is due 5 business days after the date of acceptance. Both are set by the Multi-Board 8.0 contract, which counts Monday through Friday and skips federal holidays.

During review, either attorney can approve the contract, disapprove it for a reason other than price, or propose changes. If changes or inspection requests are still unresolved 10 business days after the date of acceptance, either side can terminate. Use that week to walk the building with the person who will write the scope of work.

The form's as-is paragraph removes repair requests, but an inspection paragraph can still be initialed so you keep the right to walk. If you wrote the offer as a cash deal, the seller can ask you to prove the money, which is covered on our proof of funds page.

How fast can the loan and the purchase close?

Jaken Finance Group's published closing time is 7-10 business days on complete files, counted after borrower conditions are met. The count starts when your file is complete, so the days you control are the ones before it. The checklist of a complete file lists what a complete file holds.

Three outside parties set the rest of the pace. The seller's title company issues the title commitment. The City's Department of Finance issues the Full Payment Certificate, and its stated processing time is: Up to 10 business days; in-person may finish same day. The zoning certificate takes 5 business days for the initial decision. Ask the seller's attorney during review when each was ordered. Our page on title and City clearances explains each document, and buyers closing in an entity should have the LLC paperwork finished before the lender asks.

How long does a Chicago permit take once you apply?

The median renovation or alteration permit issued citywide in the last 24 months took 56 days from application start to issue. A quarter took 21 days or less and a quarter took more than 116. The review program explains most of that spread.

Review programPermits issued, 24 monthsMedian daysMiddle half of permits
Self-Certification4,995279 to 54 days
Standard Plan Review5,5359449 to 161 days
All renovation and alteration permits10,9045621 to 116 days

Source: City of Chicago, Department of Buildings, Building Permits (dataset ydr8-5enu), 2024-11-01 to 2026-10-31; retrieved 2026-11-26.

The table counts plan-based renovation permits from the City's building permit records. Repair work under the Express Permit Program is a separate category and is not in these medians. The Department of Buildings says self-certified applications typically issue in 10 business days after zoning approval; the recorded median starts earlier, when the application is opened. Which program your project qualifies for is the subject of our guide to DOB permit paths.

How many days should the rehab itself get?

Give the rehab the contractor's written schedule plus the City's inspection lead times. Permitted work stops at each rough inspection until an inspector signs off, and the Department of Buildings asks for At least 4 business days when you request a specific inspection date.

Lender draws add a second rhythm. Each draw reimburses finished work after an inspection, so plan phases so a request goes in the day a phase ends. The mechanics are on our page about draws and draw inspections.

What does the full calendar cost in carry?

Every day between the purchase closing and the payoff carries interest, taxes, insurance and utilities. The example prices a two-flat's hold using the citywide self-certified permit median.

Worked example

A Belmont Cragin two-flat on the calendar: 189 days, offer to payoff

Purchase $318,000, approved rehab $84,000, supported ARV $540,000, loan $370,200. Every duration except the permit median is an illustrative planning input.

Before you own it

LineAmountHow it is figured
Attorney review and inspection7 days5 business days, about 7 calendar days
Title, City certificates, loan documents, closing14 daysplanning input for a complete file
Accepted offer to purchase closing21 days

Line items sum to the stated result. Checked in code at build.

The hold: purchase closing to payoff

LineAmountHow it is figured
Permit wait, self-certified27 dayscitywide median, application start to issue
Rehab75 dayscontractor schedule, an input
Photos, listing, offer accepted21 daysan input
Resale buyer's contract to closing45 daysan input
Days of carry168 days

Line items sum to the stated result. Checked in code at build.

What 168 days of carry cost

LineAmountHow it is figured
Interest$18,141$370,200 x 10.5% / 360 = $107.98 a day x 168
Taxes, insurance, utilities$6,352$1,150 a month = $37.81 a day x 168
Added cost if the permit took the Standard Plan Review median$9,76867 more days x $145.79
Carry for the hold$24,493

Line items sum to the stated result. Checked in code at build.

Every day this project slips costs about $145.79.

Assumptions

  • The 10.5% rate is an input inside the published range of 8.99%-13.5%, not an offer. Interest is figured on the full commitment for the whole hold.
  • Permit days are the citywide median for renovation and alteration permits issued in the 24 months ending October 31, 2026.
  • Rehab, listing and buyer-side durations, and carry of $1,150 a month, are planning inputs.

The slipped-schedule calculator does that arithmetic for your loan, and month-by-month totals are on our page about total carry at each hold length.

When should the listing go live, and how long is the buyer's side?

List when the work passes final inspection and the photos are done, then expect the buyer's lender to set the pace. On the Multi-Board form a financed buyer's loan contingency date is 45 days after acceptance or 5 business days before closing, whichever is earlier.

Now you are the seller, and the seller's list is yours: a new Full Payment Certificate, a new zoning certificate, the transfer declaration, and a survey, which the contract describes as seller's expense; dated no more than 6 months before closing.

One federal rule can remove a class of buyers. Under 24 CFR 203.37a, a resale is Ineligible for FHA financing at 90 days or less.

What happens at the resale closing and payoff?

The title company handles the payoff. Your attorney requests a payoff letter from the lender before closing. It states the principal, accrued interest, any fees due under the loan documents and a per diem. Holdback money you never drew is not part of the balance.

At closing the title company wires the payoff from the buyer's funds, and the remainder is yours after transfer taxes, commission and credits. The lender's deadline to release the paid mortgage under 765 ILCS 905/4 is 30 days after payoff. If you keep the building, the payoff comes from a new loan, compared on our sale versus refinance page.

Where do Chicago flips lose the most days?

Most lost days trace to a few handoffs, and each has an owner.

Where the days goWho controls itWhat to do before it starts
City certificates ordered lateSeller's attorneyAsk on day one of attorney review for the order dates
Drawings not ready at closingYou and your architectEngage the architect during the inspection window
Wrong review programArchitectConfirm self-certification eligibility before design
Waiting for rough inspectionsGeneral contractorRequest inspections as each trade finishes, not in batches

When a 90-day plan will not hold

A budget built on a 90-day hold fails on any project that needs Standard Plan Review. The citywide median wait for that program alone is 94 days, before a single wall comes down.

The better route is to pick the timeline first and the scope second. If the numbers only work at 90 days, buy a building whose scope fits repair-level permits. If the scope needs plan review, underwrite the longer hold. The loan term is underwritten file by file, ask your loan officer, and what happens when a project outruns it is covered under extensions and maturity.

What belongs on your calendar before the contract goes out?

Build the calendar before the contract, because the contract fixes the first deadlines.

  1. Download the project timeline template and enter your own duration for each phase.
  2. Ask an architect which permit program the scope fits, and use that program's median.
  3. Price the hold per day.
  4. Line up your attorney, inspector and contractor for the five business days after acceptance.
  5. Send the address, price, scope and ARV to the lender before you sign.

Jaken Finance Group publishes its Chicago flip loan program and takes deal scenarios online. Timelines here are general education; confirm contract deadlines with your Illinois attorney.

Questions: Timeline from offer to payoff

Can I apply for the permit before I close on the purchase?

Drawings can start the day the inspection period ends, and that is where the saved time comes from. Your architect needs access to measure, so write access into the contract during attorney review. Whether an application can be filed before you hold title depends on the owner's cooperation and the Department of Buildings' requirements, so ask your architect how they handle a property under contract.

Do business days in the Illinois contract include Saturdays?

No. The Multi-Board 8.0 form defines business days as Monday through Friday, excluding federal holidays, and a deadline that lands on another day moves to the next business day. A five business day review that starts before a holiday weekend can run well past a calendar week. Count the days with your attorney on the day of acceptance, because a missed inspection notice waives the right to terminate under that paragraph.

Does an FHA buyer slow down my resale?

It can stop it. Under HUD's rule a resale is Ineligible for FHA financing at 90 days or less, measured from your acquisition to the date the buyer signs the contract. For resales in days 91 to 180, the rule is: Second appraisal if resale price is 100% or more over acquisition price. Keep your settlement statement, permits and paid invoices together so the buyer's lender can document the improvements.

How long after closing does the payoff lender release its mortgage?

The title company wires the payoff from the buyer's funds at your resale closing, using a payoff letter that states the balance and a per diem. Illinois law then gives the lender a window: 30 days after payoff, with a statutory penalty if it knowingly fails to deliver or record the release. Recording a release in Cook County costs $107 per mortgage or release.

Is winter a bad time to start the clock?

It depends on the scope. Interior work can continue through the cold months once the building is closed in and heated, while exterior masonry, concrete and roofing depend on the weather. Chicago's heat season runs September 15 to June 1, and footings must reach 42 inches below final grade. If exterior work lands in winter, sequence it first or last.

Local rates and rules cited on this page

ItemFigurePrimary sourceEffective
Attorney review period (Multi-Board contract 8.0)5 business days after the date of acceptanceMulti-Board Residential Real Estate Contract 8.0, highlighted major changes (Chicago Association of REALTORS)2025-01
Inspection notice deadline (Multi-Board contract 8.0)5 business days after the date of acceptanceMulti-Board Residential Real Estate Contract 8.0, full redline (paragraph 15, Inspections) (Chicago Association of REALTORS)2025-02
Deadline to settle attorney and inspection requests (Multi-Board 8.0)10 business days after the date of acceptanceMulti-Board Residential Real Estate Contract 8.0, full redline (paragraphs 13 and 15) (Chicago Association of REALTORS)2025-02
Full Payment Certificate processing timeUp to 10 business days; in-person may finish same dayFull Payment Certificates (City of Chicago Department of Finance)2026
Certificate of Zoning Compliance decision time5 business days for the initial decisionCertificate of Zoning Compliance (City of Chicago Department of Planning and Development)2026
Self-Certification typical issuance time10 business days after zoning approvalSelf-Certified Permit Application Program (City of Chicago Department of Buildings)2026
Permit inspection request lead timeAt least 4 business daysPermit Inspections (City of Chicago Department of Buildings)2026
Buyer's loan contingency date (Multi-Board 8.0)45 days after acceptance or 5 business days before closing, whichever is earlierMulti-Board Residential Real Estate Contract 8.0, full redline (paragraph 8, Financing) (Chicago Association of REALTORS)2025-02
Plat of survey under the Multi-Board 8.0 contractseller's expense; dated no more than 6 months before closingMulti-Board Residential Real Estate Contract 8.0, full redline (paragraph 21, Plat of Survey) (Chicago Association of REALTORS)2025-02
FHA anti-flipping: resale within 90 daysIneligible for FHA financing at 90 days or less24 CFR 203.37a - Sale of property (eCFR / HUD)2006-06-07
Lender's deadline to release a paid-off mortgage30 days after payoffMortgage Act, 765 ILCS 905/4 (Illinois General Assembly (ilga.gov))2020-01-01
FHA anti-flipping: resale in days 91-180Second appraisal if resale price is 100% or more over acquisition price24 CFR 203.37a - Sale of property (eCFR / HUD)2006-06-07
Cook County mortgage / release recording fee$107 per mortgage or releaseRecording Fees (Cook County Clerk)2024-04-01
Chicago heat seasonSeptember 15 to June 1Chicago Heat Ordinance (City of Chicago Department of Buildings)2026
Footing depth for frost protection42 inches below final gradeMunicipal Code of Chicago 14B-18-1809 Shallow foundations (American Legal Publishing (Municipal Code of Chicago))2020-08-01

Rates as of November 25, 2026. Confirm with the agency before relying on any figure.

Sources

  1. Multi-Board Residential Real Estate Contract 8.0, full redline, Chicago Association of REALTORS, 2025.
  2. Building Permits dataset, City of Chicago Department of Buildings, 2026-11.
  3. Self-Certification Permit Program, City of Chicago Department of Buildings, 2026.
  4. Permit-Related Building Inspections, City of Chicago Department of Buildings, 2026.
  5. Full Payment Certificates, City of Chicago Department of Finance, 2026.
  6. 24 CFR 203.37a, Sale of property, U.S. Department of Housing and Urban Development (eCFR), 2026.
  7. Mortgage Act, 765 ILCS 905/4, Illinois General Assembly, 2020-01-01.
Written and reviewed by Jason Taken, Principal, Jaken Finance Group. Author bio on jakenfinancegroup.com.Published November 25, 2026. Last updated November 25, 2026. Program terms as of November 26, 2026.General education only, not legal, tax or zoning advice. Confirm with local counsel or a CPA.